Avoid a $75,000+ loss from a missed deadline
Hawaii Lien Deadlines for Material Suppliers
Hawaii requires a "Notice of Unpaid Lien" to be provided to the owner before filing a lien if you don't have a direct contract.
Calculate Your Hawaii DeadlineTry 3 free (no email) + 3 more after email
Up to 6 total • no credit card
Hawaii is High Risk for Suppliers
Hawaii is High Risk for Suppliers The lien filing deadline is short: 45 days from completion of the improvement. Notice must be by personal service of Application for Lien and Notice of Lien.
Hawaii Lien Deadlines
| Deadline Type | Timing | Details |
|---|---|---|
| Preliminary/Notice | Not specified | (Do not invent) |
| Lien Filing | 45 days from completion of the improvement | Must file lien by 45 days from completion. |
| Notice Method | Personal service | Application for Lien and Notice of Lien. |
| Enforcement | 3 months from date lien attaches | Suit to enforce must be filed within 3 months. |
| Statutes | Haw. Rev. Stat. §507-41 et seq.; §507-42; §507-43; §507-44; §507-45; §507-46; §507-47; §507-48; §507-49 |
Common Supplier Mistakes in Hawaii
Hawaii Lien Deadlines
Deadline Type Timing Details Preliminary/Notice Not specified (Do not invent) Lien Filing 45 days from completion of the improvement Must file lien by 45 days from completion. Notice Method Personal service Application for Lien and Notice of Lien. Enforcement 3 months from date lien attaches Suit to enforce must be filed within 3 months. Statutes Haw. Rev. Stat. §507-41 et seq.; §507-42; §507-43; §507-44; §507-45; §507-46; §507-47; §507-48; §507-49
Missing Preliminary Notice
Failing to send the required preliminary notice is the most common reason suppliers lose their lien rights in Hawaii.
Late Lien Filing
The lien must be filed by the specific deadline. Even one day late invalidates the lien.
Missing Enforcement Deadline
Enforcement must occur within the statutory period after filing.
What notices are required?
Not specified in the provided text.
When must the lien be filed?
45 days from completion of the improvement.
What is the enforcement period?
3 months from date lien attaches.
What statutes apply?
Haw. Rev. Stat. §507-41 et seq.; §507-42; §507-43; §507-44; §507-45; §507-46; §507-47; §507-48; §507-49
Not Sure Which Deadline Applies?
Calculate your Hawaii lien deadline in seconds
Calculate Your DeadlineSelect Hawaii in the calculator to get your specific deadline
Frequently Asked Questions
Missing Preliminary Notice
Failing to send the required preliminary notice is the most common reason suppliers lose their lien rights in Hawaii.
Late Lien Filing
The lien must be filed by the specific deadline. Even one day late invalidates the lien.
What notices are required?
Not specified in the provided text.
When must the lien be filed?
45 days from completion of the improvement.
What is the enforcement period?
3 months from date lien attaches.
What statutes apply?
Haw. Rev. Stat. §507-41 et seq.; §507-42; §507-43; §507-44; §507-45; §507-46; §507-47; §507-48; §507-49
Disclaimer: This content is for informational purposes only and does not constitute legal advice.